The $2.1 million Toronto Town makeover is moving along in the planned 50m stages with a projected completion date of December.
A service relocation problem, especially the Telstra pit, west of the Pemell St intersection has meant that section was delayed.
The LMCC team are currently working on Stage 4 east of Pemell St for 50m, where the retaining walls are currently being refurbished.
Stage 5 is due to commence in July- August, on the easternmost café precinct, as it’s less busy over winter.
Overall tree numbers have been reduced from 28 to 22 with a commitment from LMCC to try and get as many as possible in as they reduce heat and provide shade.